Submitter

Submitter: Geurtz, JamesOrganization: Earthplan Design Alternatives, PA
Address: 134 W Emma AvenueCity: Springdale
State: ARZip: 72764
Phone Number: 479-756-1266E-Mail:

Project Information

Project ID: 109083Manager: Raymond Thompson
Received: 9/23/2019 12:00:00 AMDue: 10/3/2019
Logged: 9/23/2019Closed:
Classification: Water Improvemnts(Non-Subdiv.)Status: Open
  
Summary:
AP SUGAR CREEK RV PARK EIGHT INCH WATER MAIN EXTENSION, PEA RIDGE AR. TWO SETS OF PLANS SUBMITTED, $500.00 FEE PD
Assigned To: 153Action: Review, Comment and/or Approve
Date Assigned: 9/23/2019Due: 10/3/2019
Date Completed: 9/30/2019
Description:
C1Ltr 09/30/19 - Mailed 09/30/19
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 10/11/2019Due: 12/10/2019
Date Completed: 3/3/2020
Description:
30Ltr 03/03/20 - Mailed 03/03/20 30-day letter
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 3/3/2020Due: 4/12/2020
Date Completed: 6/1/2020
Description:
30-day letter followup
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 6/1/2020Due: 6/30/2020
Date Completed: 9/4/2020
Description:
Per conversation with engineer on 6/1/20, plans should be received by 6/30/20
 
Assigned To: 153Action: Review, Comment and/or Approve
Date Assigned: 9/3/2020Due: 9/13/2020
Date Completed: 9/17/2020
Description:
C2Ltr 09/17/20 - Mailed 09/17/20
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 9/17/2020Due: 11/16/2020
Date Completed: 1/28/2021
Description:
30-day letter
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 1/28/2021Due: 2/27/2021
Date Completed: 2/9/2021
Description:
30-day letter followup
 
Assigned To: 153Action: Review, Comment and/or Approve
Date Assigned: 2/9/2021Due: 2/19/2021
Date Completed: 2/26/2021
Description:
C3Ltr 02/26/21
 
Assigned To: 18Action: Supervisor Review
Date Assigned: 2/26/2021Due: 3/8/2021
Date Completed: 3/4/2021
Description:
CLOSING RCA'S DESCRIPTION: C3Ltr 02/26/21
 
Assigned To: 153Action: Finalize and Send Letter
Date Assigned: 3/4/2021Due: 3/14/2021
Date Completed: 3/4/2021
Description:
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 3/4/2021Due: 4/18/2021
Date Completed: 3/21/2021
Description:
Send 30-day letter
 
Assigned To: 153Action: Review, Comment and/or Approve
Date Assigned: 3/18/2021Due: 3/28/2021
Date Completed: 3/29/2021
Description:
C4Eml 03/29/21
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 3/29/2021Due: 4/8/2021
Date Completed: 3/30/2021
Description:
CLOSING RCA'S DESCRIPTION: C4Eml 03/29/21
 
Assigned To: 153Action: Finalize and Send Letter
Date Assigned: 3/30/2021Due: 4/9/2021
Date Completed: 3/30/2021
Description:
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 3/30/2021Due: 5/14/2021
Date Completed: 4/5/2021
Description:
Send 30-day letter
 
Assigned To: 153Action: Review, Comment and/or Approve
Date Assigned: 4/5/2021Due: 4/15/2021
Date Completed: 4/13/2021
Description:
C5Ltr 04/13/21
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 4/13/2021Due: 4/23/2021
Date Completed: 4/14/2021
Description:
CLOSING RCA'S DESCRIPTION: C5Ltr 04/13/21
 
Assigned To: 153Action: Finalize and Send Letter
Date Assigned: 4/14/2021Due: 4/24/2021
Date Completed: 4/15/2021
Description:
Send comment letter and wait for a reply.
 
Assigned To: 153Action: Reminder to follow-up
Date Assigned: 4/15/2021Due: 5/30/2021
Date Completed:
Description:
Send 30-day letter
 Back
Arkansas Department of Health
2017 Arkansas Department of Health. All Rights Reserved. | www.healthy.arkansas.gov
4815 W. Markham, Little Rock, AR 72205-3867 | 1-800-462-0599