Submitter
Submitter: Heiles, Elizabeth | Organization: Hawkins Weir Engineers |
Address: PO BOX 648 | City: Van Buren |
State: AR | Zip: 72957- |
Phone Number: (479) 474-1227 | E-Mail: |
Project Information
Project ID: 113691 | Manager: Jeff Stone |
Received: 12/17/2020 12:00:00 AM | Due: 12/27/2020 |
Logged: 12/17/2020 | Closed: |
Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Open |
Summary: | |
P STREET AND MASSARD PAA DISINFECTION IMPROVEMENTS, FT SMITH,AR. TWO SETS OF PLANS/SPECS SUBMITTED, $500.00 FEE PD. Project remained open while primary reviewer was out of office. Letter; 113691 D7 C1 - P Street and Massard PAA Disinfection Improvements - Fort Smith.doc; began on 1/7/21; TRJ. Letter: 113691 D7 A1 - P Street and Massard PAA Disinfection Improvements - Sewer Improvements - Fort Smith.docx; written 03/31/2021; TRJ. Letter; 113691 D7 C1 - P Street and Massard PAA Disinfection Improvements - Fort Smith.doc; reviewed on 1/20/21, SMY (project brought to Supervisor on 01/14/2021, supervisor on vacation until 1/19/21) Comment letter revised with remarks from SY and LAJ . 03/12/2021; TRJ. (mailed and emaild on 3/15/21; TRJ.) |
Assigned To: 43 | Action: Review, Comment and/or Approve |
Date Assigned: 12/17/2020 | Due: 12/27/2020 |
Date Completed: 1/7/2021 | |
Description: | |
Project remained open while primary reviewer was out of office. Letter; 113691 D7 C1 - P Street and Massard PAA Disinfection Improvements - Fort Smith.doc; began on 1/7/21; TRJ. |
Assigned To: 93 | Action: Supervisor Review |
Date Assigned: 1/7/2021 | Due: 1/17/2021 |
Date Completed: 1/20/2021 | |
Description: | |
Assigned To: 45 | Action: Supervisor Review |
Date Assigned: 1/20/2021 | Due: 1/30/2021 |
Date Completed: 3/8/2021 | |
Description: | |
Assigned To: 43 | Action: Finalize and Send Letter |
Date Assigned: 3/8/2021 | Due: 3/18/2021 |
Date Completed: 3/12/2021 | |
Description: | |
Comment letter revised with remarks from SY and LAJ . 03/12/2021; TRJ. |
Assigned To: 43 | Action: Reminder to follow-up |
Date Assigned: 3/12/2021 | Due: 4/26/2021 |
Date Completed: 3/15/2021 | |
Description: | |
Comment Letter (mailed and emaild on 3/15/21; TRJ.) |
Assigned To: 43 | Action: Review, Comment and/or Approve |
Date Assigned: 3/22/2021 | Due: 4/1/2021 |
Date Completed: 3/31/2021 | |
Description: | |
Letter: 113691 D7 A1 - P Street and Massard PAA Disinfection Improvements - Sewer Improvements - Fort Smith.docx; written 03/31/2021; TRJ. |
Assigned To: 93 | Action: Supervisor Review |
Date Assigned: 3/31/2021 | Due: 4/10/2021 |
Date Completed: 4/5/2021 | |
Description: | |
CLOSING RCAS DESCRIPTION: Letter: 113691 D7 A1 - P Street and Massard PAA Disinfection Improvements - Sewer Improvements - Fort Smith.docx; written 03/31/2021; TRJ. 113691A REVIEWED BY E.S. 04/05/2021. SMY |
Assigned To: 45 | Action: Supervisor Review |
Date Assigned: 4/5/2021 | Due: 4/15/2021 |
Date Completed: 4/13/2021 | |
Description: | |