Submitter

Submitter: Vetter, JimOrganization: Olsson
Address: 302 Millsap Rd.City: Fayetteville
State: ARZip: 72703-
Phone Number: (479) 790-8381E-Mail: jvetter@olsson.com

Project Information

Project ID: 121872Manager: Glenn Greenway
Received: 6/20/2022 12:00:00 AMDue: 6/30/2022
Logged: 6/20/2022Closed:
Classification: Misc. Reports Water/SewerStatus: Open
  
Summary:
Batesville Water Plant - Preliminary Engineering Report, 1755 Chaney Dr., Batesville**ONLINE** NO FEE DUE
Assigned To: 104Action: Review, Comment and/or Approve
Date Assigned: 6/20/2022Due: 6/30/2022
Date Completed: 6/27/2022
Description:
 
Assigned To: 31Action: Supervisor Review
Date Assigned: 6/27/2022Due: 7/7/2022
Date Completed: 6/29/2022
Description:
 
Assigned To: 18Action: Supervisor Review
Date Assigned: 6/29/2022Due: 7/9/2022
Date Completed: 7/7/2022
Description:
 
Assigned To: 104Action: Finalize and Send Letter
Date Assigned: 7/7/2022Due: 7/10/2022
Date Completed: 7/7/2022
Description:
Send comment letter and wait for a reply.
 
Assigned To: 104Action: Reminder to follow-up
Date Assigned: 7/7/2022Due: 8/21/2022
Date Completed: 1/11/2023
Description:
 
Assigned To: 104Action: Review, Comment and/or Approve
Date Assigned: 1/18/2023Due: 1/28/2023
Date Completed: 1/18/2023
Description:
 
Assigned To: 31Action: Supervisor Review
Date Assigned: 1/18/2023Due: 1/28/2023
Date Completed: 1/19/2023
Description:
 
Assigned To: 18Action: Supervisor Review
Date Assigned: 1/19/2023Due: 1/29/2023
Date Completed: 1/23/2023
Description:
 
Assigned To: 104Action: Finalize and Send Letter
Date Assigned: 1/23/2023Due: 1/26/2023
Date Completed:
Description:
Project manager has approved this project.