Submitter

Submitter: Pingel, KerriOrganization: Crafton Tull
Address: 901 N. 47th Street, Ste 400City: Rogers
State: ARZip: 72756-
Phone Number: (479) 636-4838E-Mail: kerri.pingel@craftontull.com

Project Information

Project ID: 128978Manager: Raymond Thompson
Received: 6/14/2023 12:00:00 AMDue: 10/14/2025
Logged: 6/14/2023Closed:
Classification: Water & Sewer Imprvmn(Non-Sub)Status: Open
  
Summary:
TB Villas on Turtle Creek, W Walnut Street, Rogers**ONLINE** Fee $500 PD
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 6/14/2023Due: 6/24/2023
Date Completed: 6/26/2023
Description:
C1Eml 6/26/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 6/26/2023Due: 7/6/2023
Date Completed: 6/27/2023
Description:
C1Eml 6/26/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 6/27/2023Due: 6/30/2023
Date Completed: 6/27/2023
Description:
Send comment letter and wait for a reply.
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 6/27/2023Due: 8/11/2023
Date Completed: 7/25/2023
Description:
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 7/18/2023Due: 7/28/2023
Date Completed: 7/26/2023
Description:
C2Ltr 7/26/23 Sent by TCB
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 7/30/2023Due: 8/5/2023
Date Completed: 7/30/2023
Description:
C2Ltr 7/26/23 Sent by TCB
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 7/30/2023Due: 8/2/2023
Date Completed: 7/31/2023
Description:
Corfirm email was sent to Engineer [RT LV]
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 7/31/2023Due: 9/14/2023
Date Completed: 8/9/2023
Description:
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 8/7/2023Due: 8/17/2023
Date Completed: 8/16/2023
Description:
C3Ltr 8/16/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 8/16/2023Due: 8/26/2023
Date Completed: 8/16/2023
Description:
C3Ltr 8/16/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 8/16/2023Due: 8/19/2023
Date Completed: 8/16/2023
Description:
Send comment letter and wait for a reply.
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 8/16/2023Due: 9/30/2023
Date Completed: 8/24/2023
Description:
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 8/21/2023Due: 8/31/2023
Date Completed: 8/24/2023
Description:
A1Ltr 8/24/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 8/24/2023Due: 9/3/2023
Date Completed: 8/24/2023
Description:
A1Ltr 8/24/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 8/24/2023Due: 8/27/2023
Date Completed: 8/24/2023
Description:
Project manager has approved this project.
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 9/19/2023Due: 9/29/2023
Date Completed: 9/20/2023
Description:
C4Eml 9/20/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 9/21/2023Due: 9/30/2023
Date Completed: 9/21/2023
Description:
C4Eml 9/20/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 9/21/2023Due: 9/24/2023
Date Completed: 9/21/2023
Description:
Send comment letter and wait for a reply.
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 9/21/2023Due: 11/5/2023
Date Completed: 9/27/2023
Description:
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 9/27/2023Due: 10/7/2023
Date Completed: 9/29/2023
Description:
C5Ltr 09/28/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 9/29/2023Due: 10/9/2023
Date Completed: 9/29/2023
Description:
C5Ltr 09/28/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 9/29/2023Due: 10/2/2023
Date Completed: 10/2/2023
Description:
Send comment letter and wait for a reply.
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 9/29/2023Due: 10/2/2023
Date Completed: 10/2/2023
Description:
Send comment letter and wait for a reply.
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 10/2/2023Due: 11/16/2023
Date Completed: 10/2/2023
Description:
 
Assigned To: 213Action: Reminder to follow-up
Date Assigned: 10/2/2023Due: 11/16/2023
Date Completed: 10/5/2023
Description:
 
Assigned To: 213Action: Review, Comment and/or Approve
Date Assigned: 10/5/2023Due: 10/15/2023
Date Completed: 10/10/2023
Description:
A2Ltr 10/10/23
 
Assigned To: 84Action: Supervisor Review
Date Assigned: 10/10/2023Due: 10/20/2023
Date Completed: 10/11/2023
Description:
A2Ltr 10/10/23
 
Assigned To: 213Action: Finalize and Send Letter
Date Assigned: 10/11/2023Due: 10/14/2023
Date Completed: 10/11/2023
Description:
Project manager has approved this project.
 
Assigned To: 237Action: Review, Comment and/or Approve
Date Assigned: 9/24/2025Due: 10/4/2025
Date Completed:
Description:
 Back
Arkansas Department of Health
© 2017 Arkansas Department of Health. All Rights Reserved. | www.healthy.arkansas.gov
4815 W. Markham, Little Rock, AR 72205-3867 | 1-800-462-0599