Submitter
| Submitter: Mullican, Wayne | Organization: SFS Security Fire Systems |
| Address: PO Box 134 | City: Alexander |
| State: AR | Zip: 72002- |
| Phone Number: (501) 737-1300 | E-Mail: wayne@sfsdfw.com |
Project Information
| Project ID: 129038 | Manager: Dennis Taylor |
| Received: 6/19/2023 12:00:00 AM | Due: 6/29/2023 |
| Logged: 6/19/2023 | Closed: |
| Classification: Water - Fire Protection | Status: Open |
| Summary: | |
| The Point at Parkway, 101 North Independance, Russellville**ONLINE** Fee $50 PD | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/19/2023 | Due: 6/29/2023 |
| Date Completed: 6/22/2023 | |
| Description: | |
| 129038C1 Sent to DET for review | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 6/22/2023 | Due: 7/2/2023 |
| Date Completed: 6/22/2023 | |
| Description: | |
| 129038C1 Sent to DET for review. 129038C1 dated 6/22/2023 OK to mail/Email/upload to portal. DET 6/22/2023. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 6/22/2023 | Due: 6/25/2023 |
| Date Completed: 6/23/2023 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 6/23/2023 | Due: 7/23/2023 |
| Date Completed: 10/23/2023 | |
| Description: | |
| 129038C1 dated 6-22-2023 emailed to Zane Bryson with City Corporation | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 10/23/2023 | Due: 11/22/2023 |
| Date Completed: 11/3/2023 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 10/30/2023 | Due: 11/9/2023 |
| Date Completed: 11/3/2023 | |
| Description: | |
| 129038C2 dated 11-06-2023 | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 11/3/2023 | Due: 11/13/2023 |
| Date Completed: 11/6/2023 | |
| Description: | |
| 129038C2 dated 11-06-2023. OK to mail/Email/upload to portal. DET 11/6/2023. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 11/6/2023 | Due: 11/9/2023 |
| Date Completed: 11/7/2023 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 11/7/2023 | Due: 12/7/2023 |
| Date Completed: 12/27/2024 | |
| Description: | |
| Assigned To: 229 | Action: 30 Day Letter |
| Date Assigned: 12/27/2024 | Due: 1/6/2025 |
| Date Completed: 12/27/2024 | |
| Description: | |
| Mailed/emailed letter dated 12-27-2024. AB | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 12/27/2024 | Due: 1/26/2025 |
| Date Completed: 2/5/2025 | |
| Description: | |
| Phone call dated 2/05/2025 to PK Development, Phillip Lewis Engineering requesting as-builts and City Corp approval for the work already completed without ADH approval. Also sent Zayne Bryson, Utility Engineer, and email requesting concurrance/approval prior to commencement of construction. AB | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 2/5/2025 | Due: 3/7/2025 |
| Date Completed: | |
| Description: | |