Submitter
| Submitter: White, Austin | Organization: Summit Fire & Security |
| Address: 5510 Landers Rd., Ste. B | City: North Little Rock |
| State: AR | Zip: 72117- |
| Phone Number: (501) 254-0781 | E-Mail: awhite@summitfiresecurity.com |
Project Information
| Project ID: 129563 | Manager: Dennis Taylor |
| Received: 8/3/2023 12:00:00 AM | Due: 8/13/2023 |
| Logged: 8/3/2023 | Closed: |
| Classification: Water - Fire Protection | Status: Open |
| Summary: | |
| RISER HARNESS FORD FIRE PROTECTION PLANS, SEARCY,AR. THREE SETS OF PLANS SUBMITTED, $50.00 FEE PD | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/3/2023 | Due: 8/13/2023 |
| Date Completed: 8/9/2023 | |
| Description: | |
| 129563C1 dated 8-9-2023 sent to supervisor for review | |
| Assigned To: 31 | Action: Supervisor Review |
| Date Assigned: 8/9/2023 | Due: 8/19/2023 |
| Date Completed: 8/9/2023 | |
| Description: | |
| 129563C1 dated 8-9-2023 sent to supervisor for review | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 8/9/2023 | Due: 8/19/2023 |
| Date Completed: 8/9/2023 | |
| Description: | |
| 129563C1 dated 8/9/2023 OK to mail/Email t engr. DT 8/9/2023. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 8/9/2023 | Due: 8/12/2023 |
| Date Completed: 8/10/2023 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 8/10/2023 | Due: 9/9/2023 |
| Date Completed: 8/10/2023 | |
| Description: | |
| Response email dated 08-10-2023 | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/10/2023 | Due: 8/20/2023 |
| Date Completed: 8/10/2023 | |
| Description: | |
| 129563C2 dated 8-10-2023 sent to supervisor for review | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 8/10/2023 | Due: 8/20/2023 |
| Date Completed: 8/14/2023 | |
| Description: | |
| 129563C2 dated 8-10-2023 sent to supervisor for review. Comments returned to Dist.Engr. DET 8/14/2023. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 8/14/2023 | Due: 8/17/2023 |
| Date Completed: 8/14/2023 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 8/14/2023 | Due: 9/28/2023 |
| Date Completed: 1/6/2025 | |
| Description: | |
| Email dated 1-06-2025 to Summit Fire & Security requesting As-builts for the fire line. AB | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 1/6/2025 | Due: 2/5/2025 |
| Date Completed: | |
| Description: | |