Submitter
| Submitter: Lemond, Stanley | Organization: Summit Fire & Security |
| Address: 5510 Landers Rd Ste B | City: North Little Rock |
| State: AR | Zip: 72117- |
| Phone Number: (501) 945-2900 | E-Mail: slemond!rfpar.com |
Project Information
| Project ID: 130123 | Manager: Dennis Taylor |
| Received: 9/19/2023 12:00:00 AM | Due: 9/29/2023 |
| Logged: 9/19/2023 | Closed: |
| Classification: Water - Fire Protection | Status: Open |
| Summary: | |
| SARACEN LAUNDRY BLDG FIRE PROTECTION PLANS, PINE BLUFF AR. THREE SETS OF PLANS SUBMITTED, $50.00 FEE PD | |
| Assigned To: 204 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/19/2023 | Due: 9/29/2023 |
| Date Completed: 9/26/2023 | |
| Description: | |
| Sent 130123 C1 to DET for review Dated 9/26/23 | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 9/26/2023 | Due: 10/6/2023 |
| Date Completed: 9/26/2023 | |
| Description: | |
| Sent 130123 C1 to DET for review Dated 9/26/23. OK to mail/Email letter to Engineer. DET 9/26/2023. | |
| Assigned To: 204 | Action: Finalize and Send Letter |
| Date Assigned: 9/26/2023 | Due: 9/29/2023 |
| Date Completed: 9/26/2023 | |
| Description: | |
| Send comment letter and wait for a reply. Sent 130123 C1 to administrative staff for mailing on 9/26/23. Emailed a copy to Stanley Lemond on 9/26/23 | |
| Assigned To: 204 | Action: Reminder to follow-up |
| Date Assigned: 9/26/2023 | Due: 11/10/2023 |
| Date Completed: 12/16/2024 | |
| Description: | |
| Waiting for response to 130123 C1 | |
| Assigned To: 204 | Action: 30 Day Letter |
| Date Assigned: 12/16/2024 | Due: 12/26/2024 |
| Date Completed: 12/16/2024 | |
| Description: | |
| Sent 130123 30D to administrative staff for mailing on 12/16/24. Emailed a copy to Stanley Lemond on 12/16/24 | |
| Assigned To: 204 | Action: Reminder to follow-up |
| Date Assigned: 12/16/2024 | Due: 1/25/2025 |
| Date Completed: 1/21/2025 | |
| Description: | |
| Waiting for response to 130123 30D | |
| Assigned To: 204 | Action: Reminder to follow-up |
| Date Assigned: 1/21/2025 | Due: 2/20/2025 |
| Date Completed: 2/20/2025 | |
| Description: | |
| Received email response on 1/20/25 stating they were waiting for Liberty Utilities approval | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 2/20/2025 | Due: 3/2/2025 |
| Date Completed: | |
| Description: | |