Submitter

Submitter: White, TaylorOrganization: MCCLELLAND CONSULTING ENGINEER
Address: 7302 Kanis RdCity: Little Rock
State: ARZip: 72204-
Phone Number: (501) 371-0272E-Mail: twhite@mce.us.com

Project Information

Project ID: 131686Manager: Dennis Taylor
Received: 2/20/2024 12:00:00 AMDue: 3/1/2024
Logged: 2/20/2024Closed: 4/25/2024
Classification: Water Improvemnts(Non-Subdiv.)Status: Closed
  
Summary:
ADC Varner Unit Water Tank Repaint, Hwy 388, Gould**ONLINE** Fee $500 PD
Assigned To: 229Action: Review, Comment and/or Approve
Date Assigned: 2/20/2024Due: 3/1/2024
Date Completed: 2/29/2024
Description:
131686C1 dated 2-29-2024 sent to supervisor for review.
 
Assigned To: 83Action: Supervisor Review
Date Assigned: 2/29/2024Due: 3/10/2024
Date Completed: 4/17/2024
Description:
131686C1 dated 2-29-2024 sent to supervisor for review.
 
Assigned To: 229Action: Review, Comment and/or Approve
Date Assigned: 3/12/2024Due: 3/22/2024
Date Completed: 3/19/2024
Description:
131686A1 dated 3-19-2024 sent to supervisor for review.
 
Assigned To: 83Action: Supervisor Review
Date Assigned: 3/19/2024Due: 3/29/2024
Date Completed: 3/20/2024
Description:
131686A1 dated 3-19-2024 sent to supervisor for review.Reviewed and forwarded to Chief Engr for concurrence, signature and stamping. DET 3/20/2024.
 
Assigned To: 18Action: Supervisor Review
Date Assigned: 3/20/2024Due: 3/30/2024
Date Completed: 4/2/2024
Description:
 
Assigned To: 229Action: Finalize and Send Letter
Date Assigned: 4/2/2024Due: 4/5/2024
Date Completed: 4/3/2024
Description:
Send comment letter and wait for a reply. #24 mesh screen is required on the roof vent, also, the screened opening shall be raised to a minimum of 24 inches above the roof if it is not already that high. The cover / shroud over the screened opening shall extend down to the bottom of the screened opening to minimize the entry of wind blown rain.
 
Assigned To: 229Action: Reminder to follow-up
Date Assigned: 4/3/2024Due: 5/3/2024
Date Completed: 4/16/2024
Description:
 
Assigned To: 229Action: Review, Comment and/or Approve
Date Assigned: 4/11/2024Due: 4/21/2024
Date Completed: 4/16/2024
Description:
131686A1 dated 4-16-2024 sent to supervisor for review.
 
Assigned To: 83Action: Supervisor Review
Date Assigned: 4/16/2024Due: 4/26/2024
Date Completed: 4/17/2024
Description:
131686A1 dated 4-16-2024 sent to supervisor for review. Before approval, need more information on which tank mixer configuration is being proposed. Comments given to D5 Engr. DET 4/17/2024.
 
Assigned To: 229Action: Finalize and Send Letter
Date Assigned: 4/17/2024Due: 4/20/2024
Date Completed: 4/17/2024
Description:
Send comment letter and wait for a reply.
 
Assigned To: 229Action: Reminder to follow-up
Date Assigned: 4/17/2024Due: 5/17/2024
Date Completed: 4/18/2024
Description:
 
Assigned To: 18Action: Supervisor Review
Date Assigned: 4/18/2024Due: 4/28/2024
Date Completed: 4/22/2024
Description:
ADC Varner Unit Water Tank Repaint, repairs, and installation of active water mixing unit. Chief Engineer final review and approval is requested =.
 
Assigned To: 229Action: Finalize and Send Letter
Date Assigned: 4/22/2024Due: 4/25/2024
Date Completed: 4/25/2024
Description:
Project manager has approved this project.