Submitter
Submitter: Menley, Wayne | Organization: Miller Newell Engineers, Inc. |
Address: PO Box 705 | City: Newport |
State: AR | Zip: 72112- |
Phone Number: (870) 523-6531 | E-Mail: milnewengr@aol.com |
Project Information
Project ID: 132087 | Manager: Jeff Stone |
Received: 3/20/2024 12:00:00 AM | Due: 3/30/2024 |
Logged: 3/20/2024 | Closed: 4/3/2024 |
Classification: Funding Application | Status: Closed |
Summary: | |
CITY OF LAMAR WWAC#7472, NEW WASTEWATER COLLECITON SYSTEM, REHAB EXISITNG WASTEWATER COLLECITON SYSTEM, REHAB WWTP. ONE REPORT SUBMITTED, NO FEES. . Leter; 132087 D7 A1 - WWAC 7472 - Concurrence - New Wastewater Collection and Rehab existing Wastewater collection System - Lamar.docx; written 03/22/2024 - TRJ. |
Assigned To: 43 | Action: Review, Comment and/or Approve |
Date Assigned: 3/20/2024 | Due: 3/30/2024 |
Date Completed: 3/22/2024 | |
Description: | |
Leter; 132087 D7 A1 - WWAC 7472 - Concurrence - New Wastewater Collection and Rehab existing Wastewater collection System - Lamar.docx; written 03/22/2024 - TRJ. |
Assigned To: 234 | Action: Supervisor Review |
Date Assigned: 3/22/2024 | Due: 4/1/2024 |
Date Completed: 3/25/2024 | |
Description: | |
Leter; 132087 D7 A1 - WWAC 7472 - Concurrence - New Wastewater Collection and Rehab existing Wastewater collection System - Lamar.docx; written 03/22/2024 - TRJ. |
Assigned To: 18 | Action: Supervisor Review |
Date Assigned: 3/25/2024 | Due: 4/4/2024 |
Date Completed: 4/3/2024 | |
Description: | |
Assigned To: 43 | Action: Finalize and Send Letter |
Date Assigned: 4/3/2024 | Due: 4/6/2024 |
Date Completed: 4/3/2024 | |
Description: | |
Project manager has approved this project. |