Submitter
| Submitter: Flood, Jacob | Organization: Utility Service Co., Inc |
| Address: 1230 Peachtree St. NE | City: Atlanta |
| State: GA | Zip: 30309- |
| Phone Number: (770) 702-4174 | E-Mail: jacob.flood@usgwater.com |
Project Information
| Project ID: 134629 | Manager: Dennis Taylor |
| Received: 7/31/2024 12:00:00 AM | Due: 8/10/2024 |
| Logged: 7/31/2024 | Closed: |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| Interior Renovation and mixer installation, Bowles Tank, City of Dumas, AR., 219 Edwards St., Dumas**ONLINE** Fee $500 pd | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/31/2024 | Due: 8/10/2024 |
| Date Completed: 8/9/2024 | |
| Description: | |
| 134629A1 dated 8-12-2024 sent to DET. AB 8-09 | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 8/9/2024 | Due: 8/19/2024 |
| Date Completed: 8/12/2024 | |
| Description: | |
| 134629C1 dated 8-12-2024 sent to DET. AB 8-09. Reviewed and forwarded to Chief Engr for concurrence. DET 8-12-2024. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 8/12/2024 | Due: 8/22/2024 |
| Date Completed: 8/23/2024 | |
| Description: | |
| Reviewed and forwarded to Chief Engr for concurrence. DET 8-12-2024. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 8/23/2024 | Due: 8/26/2024 |
| Date Completed: 8/26/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 8/26/2024 | Due: 9/25/2024 |
| Date Completed: 9/6/2024 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/28/2024 | Due: 9/7/2024 |
| Date Completed: 9/6/2024 | |
| Description: | |
| 134629A1 dated 9-09-2024 sent to supervisor. AB 9-06-2024 | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 9/6/2024 | Due: 9/16/2024 |
| Date Completed: 9/19/2024 | |
| Description: | |
| 134629A1 dated 9-09-2024 sent to supervisor. AB 9-06-2024 | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 9/10/2024 | Due: 9/20/2024 |
| Date Completed: 9/19/2024 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 9/19/2024 | Due: 9/22/2024 |
| Date Completed: 9/19/2024 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 229 | Action: Error |
| Date Assigned: 9/19/2024 | Due: 9/22/2024 |
| Date Completed: 9/19/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Error |
| Date Assigned: 9/19/2024 | Due: 9/29/2024 |
| Date Completed: 9/23/2024 | |
| Description: | |
| Assigned To: 229 | Action: Error |
| Date Assigned: 9/23/2024 | Due: 11/7/2024 |
| Date Completed: 2/6/2025 | |
| Description: | |