Submitter
| Submitter: Dreher, James | Organization: OWN Dardenelle |
| Address: 111 North Front Street | City: Dardenelle |
| State: AR | Zip: 72834- |
| Phone Number: (501) 224-1000 | E-Mail: jdreher@weareown.com |
Project Information
| Project ID: 134842 | Manager: Dennis Taylor |
| Received: 8/19/2024 12:00:00 AM | Due: 8/29/2024 |
| Logged: 8/19/2024 | Closed: |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| Water Plant Rehabilitation - MCRPWA, Scott Street, Mount Ida**ONLINE** Fee $500 PD | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/19/2024 | Due: 8/29/2024 |
| Date Completed: 8/28/2024 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 8/28/2024 | Due: 9/7/2024 |
| Date Completed: 9/4/2024 | |
| Description: | |
| Reviewed and forwarded to Chief Engr for concurrence before mailing. DET 9-4-2024. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 9/4/2024 | Due: 9/14/2024 |
| Date Completed: 9/10/2024 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 9/10/2024 | Due: 9/13/2024 |
| Date Completed: 9/10/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 9/10/2024 | Due: 10/10/2024 |
| Date Completed: 10/23/2024 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 10/18/2024 | Due: 10/28/2024 |
| Date Completed: 10/28/2024 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 10/28/2024 | Due: 11/7/2024 |
| Date Completed: 12/11/2024 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 12/3/2024 | Due: 12/13/2024 |
| Date Completed: 12/13/2024 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 12/11/2024 | Due: 12/14/2024 |
| Date Completed: 12/11/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 12/11/2024 | Due: 1/25/2025 |
| Date Completed: 2/4/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 12/13/2024 | Due: 12/23/2024 |
| Date Completed: 2/3/2025 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 2/3/2025 | Due: 2/6/2025 |
| Date Completed: 2/4/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 2/4/2025 | Due: 3/21/2025 |
| Date Completed: 2/4/2025 | |
| Description: | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 2/4/2025 | Due: 3/6/2025 |
| Date Completed: | |
| Description: | |
| Meeting with ADH staff, engineer and suppliers back on December 18, 2024. Updated plans will be submitted based on what was discussed throughout the virtual call meeting. AB | |