Submitter
| Submitter: Wastewater, MCE | Organization: MCCLELLAND CONSULTING ENGINEER |
| Address: 7302 Kanis Rd | City: Little Rock |
| State: AR | Zip: 72204- |
| Phone Number: (501) 371-0272 | E-Mail: lrww@mce.us.com |
Project Information
| Project ID: 135948 | Manager: Glenn Greenway |
| Received: 11/21/2024 12:00:00 AM | Due: 12/1/2024 |
| Logged: 11/21/2024 | Closed: |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| Liberty Utilities Highland View Water Line Extension, Gamble Road and Highland View, White Hall**ONLINE** Fee $350 pd | |
| Assigned To: 231 | Action: Review, Comment and/or Approve |
| Date Assigned: 11/21/2024 | Due: 12/1/2024 |
| Date Completed: 11/22/2024 | |
| Description: | |
| Assigned To: 31 | Action: Supervisor Review |
| Date Assigned: 11/22/2024 | Due: 12/2/2024 |
| Date Completed: 11/22/2024 | |
| Description: | |
| Assigned To: 231 | Action: Finalize and Send Letter |
| Date Assigned: 11/22/2024 | Due: 11/25/2024 |
| Date Completed: 11/25/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 231 | Action: Reminder to follow-up |
| Date Assigned: 11/25/2024 | Due: 1/9/2025 |
| Date Completed: 11/27/2024 | |
| Description: | |
| Assigned To: 231 | Action: Review, Comment and/or Approve |
| Date Assigned: 11/27/2024 | Due: 12/7/2024 |
| Date Completed: 11/27/2024 | |
| Description: | |
| Assigned To: 31 | Action: Supervisor Review |
| Date Assigned: 11/27/2024 | Due: 12/7/2024 |
| Date Completed: 12/2/2024 | |
| Description: | |
| Assigned To: 231 | Action: Finalize and Send Letter |
| Date Assigned: 12/2/2024 | Due: 12/5/2024 |
| Date Completed: 12/2/2024 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 231 | Action: Reminder to follow-up |
| Date Assigned: 12/2/2024 | Due: 1/16/2025 |
| Date Completed: 12/5/2024 | |
| Description: | |
| Assigned To: 231 | Action: Review, Comment and/or Approve |
| Date Assigned: 12/4/2024 | Due: 12/14/2024 |
| Date Completed: 12/10/2024 | |
| Description: | |
| Assigned To: 31 | Action: Supervisor Review |
| Date Assigned: 12/10/2024 | Due: 12/20/2024 |
| Date Completed: | |
| Description: | |
| Assigned To: 231 | Action: Review, Comment and/or Approve |
| Date Assigned: 12/11/2024 | Due: 12/21/2024 |
| Date Completed: 12/11/2024 | |
| Description: | |
| Assigned To: 31 | Action: Supervisor Review |
| Date Assigned: 12/11/2024 | Due: 12/21/2024 |
| Date Completed: 12/12/2024 | |
| Description: | |
| Assigned To: 231 | Action: Finalize and Send Letter |
| Date Assigned: 12/12/2024 | Due: 12/15/2024 |
| Date Completed: 12/16/2024 | |
| Description: | |
| Project manager has approved this project. | |