Submitter
| Submitter: Meyer, David | Organization: FREEDOM FIRE PRO LLC |
| Address: 811 LESTER LANE | City: ROGERS |
| State: AR | Zip: 72756- |
| Phone Number: (479) 631-6363 | E-Mail: djmeyer@freefirepro.com |
Project Information
| Project ID: 137278 | Manager: Tanner Burns |
| Received: 4/1/2025 12:00:00 AM | Due: 7/27/2025 |
| Logged: 4/1/2025 | Closed: 8/25/2025 |
| Classification: Water - Fire Protection | Status: Closed |
| Summary: | |
| Ebbing Field Air National Guard Building 115, 4850 Leigh Ave, Ft. Smith**ONLINE** Fee $50 pd. . Letter; 137278 D7 C1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 04/11/2025 - TRJ. (sent 04/21/2025) Email sent to D. Meyers at FFP concerning owner concurrence and a question about easements. Closed RCA - 07/14/2025 - TRJ. Letter; 137278 D7 A1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 08/18/2025 - TRJ. (sent 08/25/2025) | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/1/2025 | Due: 4/11/2025 |
| Date Completed: 4/11/2025 | |
| Description: | |
| Letter; 137278 D7 C1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 04/11/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 4/11/2025 | Due: 4/21/2025 |
| Date Completed: 4/15/2025 | |
| Description: | |
| Letter; 137278 D7 C1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 04/11/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 4/15/2025 | Due: 4/18/2025 |
| Date Completed: 4/21/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 137278 D7 C1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 04/11/2025 - TRJ. (sent 04/21/2025) | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 4/21/2025 | Due: 6/5/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/7/2025 | Due: 7/17/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Email sent to D. Meyers at FFP concerning owner concurrence and a question about easements. Closed RCA - 07/14/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 7/14/2025 | Due: 7/24/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Email sent to D. Meyers at FFP concerning owner concurrence and a question about easements. Closed RCA - 07/14/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 7/14/2025 | Due: 7/17/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 7/14/2025 | Due: 8/28/2025 |
| Date Completed: 8/18/2025 | |
| Description: | |
| Response received . Letter; 137278 D7 A1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 08/18/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 8/18/2025 | Due: 8/28/2025 |
| Date Completed: 8/20/2025 | |
| Description: | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 8/20/2025 | Due: 8/23/2025 |
| Date Completed: 8/25/2025 | |
| Description: | |
| Project manager has approved this project. Letter; 137278 D7 A1 FP - Ebbing Field Air National Guard Building 115 - Water Improvements - Fort Smith .docx; written 08/18/2025 - TRJ. (sent 08/25/2025) | |