Submitter
| Submitter: Wastewater, MCE | Organization: MCCLELLAND CONSULTING ENGINEERS |
| Address: 7302 Kanis Rd | City: Little Rock |
| State: AR | Zip: 72204- |
| Phone Number: (501) 371-0272 | E-Mail: lrww@mce.us.com |
Project Information
| Project ID: 137386 | Manager: Tanner Burns |
| Received: 4/9/2025 12:00:00 AM | Due: 7/15/2025 |
| Logged: 4/9/2025 | Closed: 7/1/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| Waldron WTP Filter Improvements, 106 E. Water Street, Waldron**ONLINE** Fee $500 pd. . Letter; 137386 D7 C1 Waldron WTP Filter Improvements - Waldron.docx; written 04/18/2025 - TRJ (received comment from TCB and CSC, updated C1 and sent out on 05-09-2025 - TRJ) Letter; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; written 05/29/2025 - TRJ. (NOT SENT). Letter; 137386 D7 C2 Waldron WTP Filter Improvements - Waldron.docx - written 06/09/2025 - TRJ. 06-20-2025 - email sent to D. Hernandez MCE concerning issues with specifications. TRJ. 06/25/20258 - Letter ; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; updated; -TRJ. (sent 07/01/2025) | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/9/2025 | Due: 4/19/2025 |
| Date Completed: 4/18/2025 | |
| Description: | |
| Letter; 137386 D7 C1 Waldron WTP Filter Improvements - Waldron.docx; written 04/18/2025 - TRJ | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 4/18/2025 | Due: 4/28/2025 |
| Date Completed: 4/24/2025 | |
| Description: | |
| Letter; 137386 D7 C1 Waldron WTP Filter Improvements - Waldron.docx; written 04/18/2025 - TRJ | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 4/24/2025 | Due: 5/4/2025 |
| Date Completed: 5/9/2025 | |
| Description: | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 5/9/2025 | Due: 5/12/2025 |
| Date Completed: 5/9/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 137386 D7 C1 Waldron WTP Filter Improvements - Waldron.docx; written 04/18/2025 - TRJ (received comment from TCB and CSC, updated C1 and sent out on 05-09-2025 - TRJ) | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 5/9/2025 | Due: 6/23/2025 |
| Date Completed: 5/28/2025 | |
| Description: | |
| response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/22/2025 | Due: 6/1/2025 |
| Date Completed: 5/29/2025 | |
| Description: | |
| Letter; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; written 05/29/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 5/29/2025 | Due: 6/8/2025 |
| Date Completed: 5/29/2025 | |
| Description: | |
| Letter; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; written 05/29/2025 - TRJ. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 5/29/2025 | Due: 6/8/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 6/6/2025 | Due: 6/9/2025 |
| Date Completed: 6/9/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 137386 D7 C2 Waldron WTP Filter Improvements - Waldron.docx - written 06/09/2025 - TRJ. | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 6/9/2025 | Due: 7/24/2025 |
| Date Completed: 6/20/2025 | |
| Description: | |
| response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/20/2025 | Due: 6/30/2025 |
| Date Completed: 6/20/2025 | |
| Description: | |
| 06-20-2025 - email sent to D. Hernandez MCE concerning issues with specifications. TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 6/20/2025 | Due: 6/30/2025 |
| Date Completed: 6/20/2025 | |
| Description: | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 6/20/2025 | Due: 6/23/2025 |
| Date Completed: 6/23/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 6/23/2025 | Due: 8/7/2025 |
| Date Completed: 6/25/2025 | |
| Description: | |
| Response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/25/2025 | Due: 7/5/2025 |
| Date Completed: 6/25/2025 | |
| Description: | |
| 06/25/20258 - Letter ; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; updated; -TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 6/25/2025 | Due: 7/5/2025 |
| Date Completed: 6/26/2025 | |
| Description: | |
| 06/25/20258 - Letter ; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; updated; -TRJ. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 6/26/2025 | Due: 7/6/2025 |
| Date Completed: 7/1/2025 | |
| Description: | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 7/1/2025 | Due: 7/4/2025 |
| Date Completed: 7/1/2025 | |
| Description: | |
| Project manager has approved this project. 06/25/20258 - Letter ; 137386 D7 A1 Waldron WTP Filter Improvements - Waldron.docx; updated; -TRJ. (sent 07/01/2025) | |