Submitter
| Submitter: Wastewater, MCE | Organization: MCCLELLAND CONSULTING ENGINEER |
| Address: 7302 Kanis Rd | City: Little Rock |
| State: AR | Zip: 72204- |
| Phone Number: (501) 371-0272 | E-Mail: lrww@mce.us.com |
Project Information
| Project ID: 137442 | Manager: Dennis Taylor |
| Received: 4/14/2025 12:00:00 AM | Due: 6/11/2025 |
| Logged: 4/14/2025 | Closed: 6/11/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| Gillham Waterline Improvements , Hornburg st, Gillham **ONLINE** Fee $500 pd | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/14/2025 | Due: 4/24/2025 |
| Date Completed: 4/16/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 4/16/2025 | Due: 4/26/2025 |
| Date Completed: 4/17/2025 | |
| Description: | |
| 137442A1 OK to mail/Email/upload to portal. DET 4-17-2025 | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 4/17/2025 | Due: 4/20/2025 |
| Date Completed: 4/18/2025 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 4/18/2025 | Due: 5/18/2025 |
| Date Completed: 5/22/2025 | |
| Description: | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/22/2025 | Due: 6/1/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 6/6/2025 | Due: 6/16/2025 |
| Date Completed: 6/9/2025 | |
| Description: | |
| 137442A1 dated 6-9-2025 signed, stamped, plan review updated, OK to mail/Email/upload to portal. DET 6-9-2025. | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 6/9/2025 | Due: 6/12/2025 |
| Date Completed: 6/11/2025 | |
| Description: | |
| Project manager has approved this project. | |