Project Information
| Project ID: 137461 | Manager: Dennis Taylor |
| Received: 4/15/2025 12:00:00 AM | Due: 5/18/2025 |
| Logged: 4/15/2025 | Closed: 5/7/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| ARDOT Job 020771 - Water Line Relocation, Mist - Montrose - Snyder - Hwy 82, Hamburg**ONLINE** Fee $500 pd | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/15/2025 | Due: 4/25/2025 |
| Date Completed: 4/24/2025 | |
| Description: | |
| 137461C1 dated 4-24-2025 sent to supervisor. AB | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 4/24/2025 | Due: 5/4/2025 |
| Date Completed: 4/24/2025 | |
| Description: | |
| 137461C1 dated 4-24-2025 sent to supervisor. AB Reviewed and comments given to D5 Engr. DET 4-24-2025. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 4/24/2025 | Due: 4/27/2025 |
| Date Completed: 4/25/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 4/25/2025 | Due: 5/25/2025 |
| Date Completed: 5/1/2025 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/28/2025 | Due: 5/8/2025 |
| Date Completed: 5/7/2025 | |
| Description: | |
| 137461A1 Draft dated 5-07-2025 sent to supervisor. AB | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 5/7/2025 | Due: 5/17/2025 |
| Date Completed: 5/7/2025 | |
| Description: | |
| 137461A1 Draft dated 5-07-2025 sent to supervisor. AB letter dated 5-7-2025 signed, plns stamped, plan review updated, OK to mail, Email, upload to portal. DET 5-7-2025. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 5/7/2025 | Due: 5/10/2025 |
| Date Completed: 5/7/2025 | |
| Description: | |
| Project manager has approved this project. | |