Submitter
| Submitter: Awhitehurst, Awhitehurst | Organization: A.L. Franks Engineering, Inc. |
| Address: 118 East Broad Street | City: Texarkana |
| State: AR | Zip: 71854- |
| Phone Number: (870) 216-1906 | E-Mail: awhitehurst@alfranksengineering.com |
Project Information
| Project ID: 137488 | Manager: Dennis Taylor |
| Received: 4/17/2025 12:00:00 AM | Due: 7/2/2025 |
| Logged: 4/17/2025 | Closed: |
| Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| Dierks Wastewater Improvements, 220 W. Second Street, Dierks**ONLINE** Fee $500 PD | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/17/2025 | Due: 4/27/2025 |
| Date Completed: 4/25/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 4/25/2025 | Due: 5/5/2025 |
| Date Completed: 4/25/2025 | |
| Description: | |
| 137488C! dated 4-25-2025 reviewed and forwarded to Chief Engr for comment. This project replaces significant portion of Dierks Sewer Collection System. DET 4-25-2025. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 4/25/2025 | Due: 5/5/2025 |
| Date Completed: 5/12/2025 | |
| Description: | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 5/12/2025 | Due: 5/15/2025 |
| Date Completed: 5/19/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 5/19/2025 | Due: 7/3/2025 |
| Date Completed: 7/7/2025 | |
| Description: | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/12/2025 | Due: 6/22/2025 |
| Date Completed: 7/9/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 7/9/2025 | Due: 7/19/2025 |
| Date Completed: 7/9/2025 | |
| Description: | |
| 137488C2 dated 7-9-2025 reviewed and forwarded to Chief Engr for comment. This project replaces a significant portion of Dierks Sewer Collection System. DET 7-9-2025. | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 7/9/2025 | Due: 7/19/2025 |
| Date Completed: 7/17/2025 | |
| Description: | |
| 137488C2 dated 7-9-2025 reviewed and forwarded to Chief Engr for comment. This project replaces a significant portion of Dierks Sewer Collection System. DET 7-9-2025. | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 7/17/2025 | Due: 7/20/2025 |
| Date Completed: 7/25/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 7/25/2025 | Due: 9/8/2025 |
| Date Completed: 7/25/2025 | |
| Description: | |