Project ID: 137551Manager: Jake Chatman
Received: 4/23/2025 12:00:00 AMDue: 5/29/2025
Logged: 4/23/2025Closed: 5/19/2025
Classification: Water Improvemnts(Non-Subdiv.)Status: Closed
  
Summary:
MIKE TACKETT WATERLINE EXTENSION, COMMUNITY WATER SYSTEM. TWO SETS OF PLANS/SPECS SUBIMTTED, $170.00 FEE PD
Assigned To: 222Action: Review, Comment and/or Approve
Date Assigned: 4/23/2025Due: 5/3/2025
Date Completed: 4/25/2025
Description:
 
Assigned To: 192Action: Supervisor Review
Date Assigned: 4/25/2025Due: 5/5/2025
Date Completed: 5/5/2025
Description:
 
Assigned To: 222Action: Finalize and Send Letter
Date Assigned: 5/5/2025Due: 5/8/2025
Date Completed: 5/5/2025
Description:
Send comment letter and wait for a reply.
 
Assigned To: 222Action: Reminder to follow-up
Date Assigned: 5/5/2025Due: 6/19/2025
Date Completed: 5/12/2025
Description:
 
Assigned To: 222Action: Review, Comment and/or Approve
Date Assigned: 5/9/2025Due: 5/19/2025
Date Completed: 5/12/2025
Description:
 
Assigned To: 192Action: Supervisor Review
Date Assigned: 5/12/2025Due: 5/22/2025
Date Completed: 5/19/2025
Description:
 
Assigned To: 222Action: Finalize and Send Letter
Date Assigned: 5/19/2025Due: 5/22/2025
Date Completed: 5/19/2025
Description:
Project manager has approved this project.