Submitter
| Submitter: Franks, Anthony L | Organization: A.L. Franks Engineering |
| Address: 118 E Broad Street | City: Texarkana |
| State: AR | Zip: 71854- |
| Phone Number: (870) 216-1906 | E-Mail: |
Project Information
| Project ID: 137553 | Manager: Dennis Taylor |
| Received: 4/23/2025 12:00:00 AM | Due: 6/18/2025 |
| Logged: 4/23/2025 | Closed: 6/6/2025 |
| Classification: Funding Application | Status: Closed |
| Summary: | |
| CITY OF MAGNOLIA WWAC#7597, NEW WATER STORAGE TANK. ONE REPORT SUBMITTED, $NO FEE | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/23/2025 | Due: 5/3/2025 |
| Date Completed: 4/25/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 4/25/2025 | Due: 5/5/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 5/1/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 5/8/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 5/8/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 5/8/2025 | Due: 6/22/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Assigned To: 248 | Action: Reminder to follow-up |
| Date Assigned: 5/8/2025 | Due: 6/22/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/29/2025 | Due: 6/8/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| See the responce documents in the WWAC folder for May 2025 | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 6/2/2025 | Due: 6/12/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 6/6/2025 | Due: 6/16/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| See the responce documents in the WWAC folder for May 2025 | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 6/6/2025 | Due: 6/9/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 6/6/2025 | Due: 6/9/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Project manager has approved this project. | |