Submitter
| Submitter: Bolin, Michael | Organization: Michael Bolin & Associates, Inc. |
| Address: PO Box 605 | City: Benton |
| State: AR | Zip: 72018-0605 |
| Phone Number: (501) 776-2692 | E-Mail: |
Project Information
| Project ID: 137556 | Manager: Dennis Taylor |
| Received: 4/23/2025 12:00:00 AM | Due: 6/5/2025 |
| Logged: 4/23/2025 | Closed: 6/6/2025 |
| Classification: Funding Application | Status: Closed |
| Summary: | |
| KIMZEY REGIONAL WATER DISTRICT WWAC#7600, NEW WATER DISTRIBUTION SYSTEM/WATER STORAGE TANK. ONE REPORT SUBMITTED,NO FEE | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/23/2025 | Due: 5/3/2025 |
| Date Completed: 5/1/2025 | |
| Description: | |
| 137556 Concur for WWAC 7600 sent to DET. AB | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 5/1/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| 137556 Concur for WWAC 7600 sent to DET. AB | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 5/8/2025 | Due: 5/18/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 5/8/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 5/8/2025 | Due: 6/22/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 5/8/2025 | Due: 5/11/2025 |
| Date Completed: 5/8/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 229 | Action: Reminder to follow-up |
| Date Assigned: 5/8/2025 | Due: 6/22/2025 |
| Date Completed: 5/22/2025 | |
| Description: | |
| Assigned To: 229 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/16/2025 | Due: 5/26/2025 |
| Date Completed: 5/23/2025 | |
| Description: | |
| 137556 Concur Letter for WACC # 7600 dated 5-23-2025 sent to DET. AB | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 5/23/2025 | Due: 6/2/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| 137556 Concur Letter for WACC # 7600 dated 5-23-2025 sent to DET. AB | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 6/2/2025 | Due: 6/12/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 6/6/2025 | Due: 6/9/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 229 | Action: Finalize and Send Letter |
| Date Assigned: 6/6/2025 | Due: 6/9/2025 |
| Date Completed: 6/6/2025 | |
| Description: | |
| Project manager has approved this project. | |