Submitter
| Submitter: Haley, Joshua | Organization: ENGINEERING SERVICES INC |
| Address: 1207 S. OLD MISSOURI ROAD | City: SPRINGDALE |
| State: AR | Zip: 72764- |
| Phone Number: (479) 751-8733 | E-Mail: jhaley@engineeringservices.com |
Project Information
| Project ID: 137619 | Manager: Dean Gernon |
| Received: 4/29/2025 12:00:00 AM | Due: 7/21/2025 |
| Logged: 4/29/2025 | Closed: 7/10/2025 |
| Classification: Sub. Public Water, Pub Sewer | Status: Closed |
| Summary: | |
| Harper Subdivision, NW Corner of Butterfield Coach Road and Zion Road, Fayetteville**ONLINE** Fee $500 pd | |
| Assigned To: 153 | Action: Review, Comment and/or Approve |
| Date Assigned: 4/29/2025 | Due: 5/9/2025 |
| Date Completed: 5/9/2025 | |
| Description: | |
| C1Ltr 05/09/25 | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 5/9/2025 | Due: 5/19/2025 |
| Date Completed: 5/19/2025 | |
| Description: | |
| C1Ltr 05/09/25 | |
| Assigned To: 153 | Action: Finalize and Send Letter |
| Date Assigned: 5/19/2025 | Due: 5/22/2025 |
| Date Completed: 5/20/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 153 | Action: Reminder to follow-up |
| Date Assigned: 5/20/2025 | Due: 7/4/2025 |
| Date Completed: 6/2/2025 | |
| Description: | |
| Assigned To: 153 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/2/2025 | Due: 6/12/2025 |
| Date Completed: 6/12/2025 | |
| Description: | |
| C2Ltr 06/12/25 | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 6/12/2025 | Due: 6/22/2025 |
| Date Completed: 6/17/2025 | |
| Description: | |
| C2Ltr 06/12/25 | |
| Assigned To: 153 | Action: Finalize and Send Letter |
| Date Assigned: 6/17/2025 | Due: 6/20/2025 |
| Date Completed: 6/17/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 153 | Action: Reminder to follow-up |
| Date Assigned: 6/17/2025 | Due: 8/1/2025 |
| Date Completed: 6/24/2025 | |
| Description: | |
| Assigned To: 153 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/24/2025 | Due: 7/4/2025 |
| Date Completed: 6/27/2025 | |
| Description: | |
| C3Eml 06/27/25 | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 6/27/2025 | Due: 7/7/2025 |
| Date Completed: 6/30/2025 | |
| Description: | |
| C3Eml 06/27/25 | |
| Assigned To: 153 | Action: Finalize and Send Letter |
| Date Assigned: 6/30/2025 | Due: 7/3/2025 |
| Date Completed: 6/30/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 153 | Action: Reminder to follow-up |
| Date Assigned: 6/30/2025 | Due: 8/14/2025 |
| Date Completed: 7/1/2025 | |
| Description: | |
| Assigned To: 153 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/1/2025 | Due: 7/11/2025 |
| Date Completed: 7/7/2025 | |
| Description: | |
| A1Ltr 07/07/25 | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 7/7/2025 | Due: 7/17/2025 |
| Date Completed: 7/10/2025 | |
| Description: | |
| A1Ltr 07/07/25. Stamped plans and specs and uploaded to the portal. Mailed, emailed, uploaded letter on 7/10/25 | |
| Assigned To: 153 | Action: Finalize and Send Letter |
| Date Assigned: 7/10/2025 | Due: 7/13/2025 |
| Date Completed: 7/10/2025 | |
| Description: | |
| Project manager has approved this project. | |