Submitter
| Submitter: , Taylor | Organization: Natural State Engineering, PLL |
| Address: 118 West North Drive | City: Rogers |
| State: AR | Zip: 72756- |
| Phone Number: (479) 391-9225 | E-Mail: taylor@naturalstateengineering.net |
Project Information
| Project ID: 137882 | Manager: Jeff Stone |
| Received: 5/19/2025 12:00:00 AM | Due: 8/12/2025 |
| Logged: 5/19/2025 | Closed: 8/8/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| Sugar Creek Water Extension, 13677 SUGAR CREEK RD, Rogers**ONLINE** Fee $100 PD | |
| Assigned To: 156 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/19/2025 | Due: 5/29/2025 |
| Date Completed: 5/23/2025 | |
| Description: | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 5/23/2025 | Due: 6/2/2025 |
| Date Completed: 5/27/2025 | |
| Description: | |
| A1 drafted | |
| Assigned To: 156 | Action: Finalize and Send Letter |
| Date Assigned: 5/27/2025 | Due: 5/30/2025 |
| Date Completed: 5/30/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 156 | Action: Reminder to follow-up |
| Date Assigned: 5/30/2025 | Due: 6/9/2025 |
| Date Completed: 5/30/2025 | |
| Description: | |
| Assigned To: 156 | Action: Reminder to follow-up |
| Date Assigned: 5/30/2025 | Due: 7/14/2025 |
| Date Completed: 7/23/2025 | |
| Description: | |
| Assigned To: 156 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/23/2025 | Due: 8/2/2025 |
| Date Completed: 7/23/2025 | |
| Description: | |
| A1 drafted | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 7/23/2025 | Due: 8/2/2025 |
| Date Completed: 7/23/2025 | |
| Description: | |
| A1 drafted | |
| Assigned To: 156 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/23/2025 | Due: 8/2/2025 |
| Date Completed: 8/8/2025 | |
| Description: | |
| Assigned To: 156 | Action: Finalize and Send Letter |
| Date Assigned: 7/23/2025 | Due: 7/26/2025 |
| Date Completed: 8/8/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 8/8/2025 | Due: 8/18/2025 |
| Date Completed: 8/8/2025 | |
| Description: | |
| A1 redrafted | |
| Assigned To: 156 | Action: Reminder to follow-up |
| Date Assigned: 8/8/2025 | Due: 9/22/2025 |
| Date Completed: 8/8/2025 | |
| Description: | |
| Assigned To: 156 | Action: Finalize and Send Letter |
| Date Assigned: 8/8/2025 | Due: 8/11/2025 |
| Date Completed: 8/8/2025 | |
| Description: | |
| Project manager has approved this project. | |