Submitter
| Submitter: Brock, Bobby J | Organization: Brock Engineering |
| Address: 95 Evergreen Dr. | City: Heber Springs |
| State: AR | Zip: 72543 |
| Phone Number: 501-2501290 | E-Mail: |
Project Information
| Project ID: 137897 | Manager: Jake Chatman |
| Received: 5/20/2025 12:00:00 AM | Due: 8/21/2025 |
| Logged: 5/20/2025 | Closed: 8/4/2025 |
| Classification: Sub. Public Water, Pub Sewer | Status: Closed |
| Summary: | |
| SUMMER WOODS SUBDIVISION WATER AND SEWER EXTENSIONS, QUITMAN AR. TWO SETS OF PLANS/SPECS SUBMITTED, $500.00 FEE PD | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 5/20/2025 | Due: 5/30/2025 |
| Date Completed: 5/28/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 5/28/2025 | Due: 6/7/2025 |
| Date Completed: 6/2/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 6/2/2025 | Due: 6/5/2025 |
| Date Completed: 6/3/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 222 | Action: Reminder to follow-up |
| Date Assigned: 6/3/2025 | Due: 7/18/2025 |
| Date Completed: 6/18/2025 | |
| Description: | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/17/2025 | Due: 6/27/2025 |
| Date Completed: 6/26/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 6/26/2025 | Due: 7/6/2025 |
| Date Completed: 7/1/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 7/1/2025 | Due: 7/4/2025 |
| Date Completed: 7/1/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 222 | Action: Reminder to follow-up |
| Date Assigned: 7/1/2025 | Due: 8/15/2025 |
| Date Completed: 7/16/2025 | |
| Description: | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/11/2025 | Due: 7/21/2025 |
| Date Completed: 7/21/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 7/21/2025 | Due: 7/31/2025 |
| Date Completed: 7/25/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 7/25/2025 | Due: 7/28/2025 |
| Date Completed: 7/25/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 222 | Action: Reminder to follow-up |
| Date Assigned: 7/25/2025 | Due: 9/8/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/28/2025 | Due: 8/7/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Email resubmittal received on 7/25/2025. -SF | |
| Assigned To: 192 | Action: Error |
| Date Assigned: 7/28/2025 | Due: 8/7/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Email resubmittal received on 7/25/2025. -SF | |
| Assigned To: 222 | Action: Reminder to follow-up |
| Date Assigned: 7/28/2025 | Due: 8/27/2025 |
| Date Completed: 8/1/2025 | |
| Description: | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/1/2025 | Due: 8/11/2025 |
| Date Completed: 8/1/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 8/1/2025 | Due: 8/11/2025 |
| Date Completed: 8/1/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 8/1/2025 | Due: 8/4/2025 |
| Date Completed: 8/1/2025 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 192 | Action: Billing |
| Date Assigned: 8/1/2025 | Due: 9/15/2025 |
| Date Completed: 8/4/2025 | |
| Description: | |
| Assigned To: 192 | Action: Billing |
| Date Assigned: 8/1/2025 | Due: 8/11/2025 |
| Date Completed: 8/4/2025 | |
| Description: | |