Submitter
| Submitter: Fletcher, Lisa | Organization: Schelle Architect PLLC |
| Address: P.O. Box 37 | City: Cabot |
| State: AR | Zip: 72023- |
| Phone Number: (501) 843-7931 | E-Mail: schellearchitect@gmail.com |
Project Information
| Project ID: 138078 | Manager: Jake Chatman |
| Received: 6/5/2025 12:00:00 AM | Due: 8/26/2025 |
| Logged: 6/5/2025 | Closed: 8/26/2025 |
| Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Closed |
| Summary: | |
| RMTC Barracks 1640B 16th Street Camp JT Robinson, NLR Pd $500 under plumbing 137641 | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/5/2025 | Due: 6/15/2025 |
| Date Completed: 6/17/2025 | |
| Description: | |
| C1 to JTC 6/17/25 | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 6/17/2025 | Due: 6/27/2025 |
| Date Completed: 6/23/2025 | |
| Description: | |
| C1 to JTC 6/17/25 | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 6/23/2025 | Due: 6/26/2025 |
| Date Completed: 6/25/2025 | |
| Description: | |
| Send comment letter and wait for reply | |
| Assigned To: 210 | Action: Reminder to follow-up |
| Date Assigned: 6/25/2025 | Due: 8/9/2025 |
| Date Completed: 7/25/2025 | |
| Description: | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/23/2025 | Due: 8/2/2025 |
| Date Completed: 7/29/2025 | |
| Description: | |
| C2 to JTC 7/29/25 also emailed the engineer & submitter with the preliminary comments on 7/29/25 | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 7/29/2025 | Due: 8/8/2025 |
| Date Completed: 8/4/2025 | |
| Description: | |
| C2 to JTC 7/29/25 also emailed the engineer & submitter with the preliminary comments on 7/29/25 | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 8/4/2025 | Due: 8/7/2025 |
| Date Completed: 8/5/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 210 | Action: Reminder to follow-up |
| Date Assigned: 8/5/2025 | Due: 9/19/2025 |
| Date Completed: 8/6/2025 | |
| Description: | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/6/2025 | Due: 8/16/2025 |
| Date Completed: 8/18/2025 | |
| Description: | |
| A1 to JTC 8/18/25 All comment addressed, will be approved. Had to email me the documents because couldnt upload to the portal. | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 8/18/2025 | Due: 8/28/2025 |
| Date Completed: 8/20/2025 | |
| Description: | |
| A1 to JTC 8/18/25 All comment addressed, will be approved. Had to email me the documents because couldnt upload to the portal. | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 8/20/2025 | Due: 8/23/2025 |
| Date Completed: 8/26/2025 | |
| Description: | |
| Project manager has approved this project. | |