Submitter
| Submitter: Pownall, JOHN | Organization: THOMAS ENGINEERING CO |
| Address: 3810 LOOKOUT RD | City: N LITTLE ROCK |
| State: AR | Zip: 72116- |
| Phone Number: (501) 753-4463 | E-Mail: thomas@thomasengineering2000.com |
Project Information
| Project ID: 138134 | Manager: Jake Chatman |
| Received: 6/11/2025 12:00:00 AM | Due: 10/14/2025 |
| Logged: 6/11/2025 | Closed: |
| Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| STONE VALLEY ADDITION, MARYLAND - STONE VALLEY , SHERWOOD**ONLINE** Fee $500 pd | |
| Assigned To: 210 | Action: Error |
| Date Assigned: 6/11/2025 | Due: 6/21/2025 |
| Date Completed: 6/23/2025 | |
| Description: | |
| Submitted the files for Tempo Hotel (138136 - which those files are the same as in this 138134), so I emailed engineer on 6/23/25 and asked for them to submit the correct files. | |
| Assigned To: 192 | Action: Error |
| Date Assigned: 6/23/2025 | Due: 7/3/2025 |
| Date Completed: 6/27/2025 | |
| Description: | |
| Submitted the files for Tempo Hotel (138136 - which those files are the same as in this 138134), so I emailed engineer on 6/23/25 and asked for them to submit the correct files. | |
| Assigned To: 210 | Action: Reminder to follow-up |
| Date Assigned: 6/27/2025 | Due: 7/7/2025 |
| Date Completed: 7/21/2025 | |
| Description: | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/11/2025 | Due: 7/21/2025 |
| Date Completed: 7/24/2025 | |
| Description: | |
| C1 to JTC 7/24/25 Recieved correct plans by email. | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 7/24/2025 | Due: 8/3/2025 |
| Date Completed: 7/30/2025 | |
| Description: | |
| C1 to JTC 7/24/25 Recieved correct plans by email. | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 7/30/2025 | Due: 8/2/2025 |
| Date Completed: 8/5/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 210 | Action: Reminder to follow-up |
| Date Assigned: 8/5/2025 | Due: 9/19/2025 |
| Date Completed: 8/26/2025 | |
| Description: | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/8/2025 | Due: 8/18/2025 |
| Date Completed: 8/26/2025 | |
| Description: | |
| A1 to JTC 8/26/25 | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 8/26/2025 | Due: 9/5/2025 |
| Date Completed: 8/26/2025 | |
| Description: | |
| A1 to JTC 8/26/25 | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 8/26/2025 | Due: 8/29/2025 |
| Date Completed: 8/29/2025 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/9/2025 | Due: 9/19/2025 |
| Date Completed: 9/11/2025 | |
| Description: | |
| Modifications sent to NLRWWU on 9/9/25 invalidate the approval issued by ADH on 8/26/25. Requested updated plans be sent to ADH for a new approval to be issued based on the updated plans. | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/10/2025 | Due: 9/20/2025 |
| Date Completed: 9/16/2025 | |
| Description: | |
| A2 to JTC 9/16/25 | |
| Assigned To: 192 | Action: Error |
| Date Assigned: 9/11/2025 | Due: 9/21/2025 |
| Date Completed: 9/19/2025 | |
| Description: | |
| Modifications sent to NLRWWU on 9/9/25 invalidate the approval issued by ADH on 8/26/25. Requested updated plans be sent to ADH for a new approval to be issued based on the updated plans. | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 9/16/2025 | Due: 9/26/2025 |
| Date Completed: 9/19/2025 | |
| Description: | |
| A2 to JTC 9/16/25 | |
| Assigned To: 210 | Action: Finalize and Send Letter |
| Date Assigned: 9/19/2025 | Due: 9/22/2025 |
| Date Completed: 9/23/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 210 | Action: Reminder to follow-up |
| Date Assigned: 9/23/2025 | Due: 11/7/2025 |
| Date Completed: | |
| Description: | |
| Assigned To: 210 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/24/2025 | Due: 10/4/2025 |
| Date Completed: | |
| Description: | |