Submitter
| Submitter: Weaver, Douglas | Organization: Weaver Engineering LLC |
| Address: 3907 Harvest Lane | City: Frisco |
| State: TX | Zip: 75034- |
| Phone Number: (501) 428-0470 | E-Mail: doug@weaver-eng.com |
Project Information
| Project ID: 138367 | Manager: Jake Chatman |
| Received: 6/26/2025 12:00:00 AM | Due: 8/17/2025 |
| Logged: 6/26/2025 | Closed: 7/31/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| West Webco Farm Road Waterline, Between Naylor Road & Bull Creek Road, Vilonia**ONLINE** Fee $500 pd | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/26/2025 | Due: 7/6/2025 |
| Date Completed: 7/3/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 7/3/2025 | Due: 7/13/2025 |
| Date Completed: 7/9/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 7/9/2025 | Due: 7/12/2025 |
| Date Completed: 7/9/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 222 | Action: Reminder to follow-up |
| Date Assigned: 7/9/2025 | Due: 8/23/2025 |
| Date Completed: 7/18/2025 | |
| Description: | |
| Assigned To: 222 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/16/2025 | Due: 7/26/2025 |
| Date Completed: 7/24/2025 | |
| Description: | |
| Assigned To: 192 | Action: Supervisor Review |
| Date Assigned: 7/24/2025 | Due: 8/3/2025 |
| Date Completed: 7/30/2025 | |
| Description: | |
| Assigned To: 222 | Action: For Your Information |
| Date Assigned: 7/28/2025 | Due: 8/7/2025 |
| Date Completed: 7/31/2025 | |
| Description: | |
| Assigned To: 222 | Action: Finalize and Send Letter |
| Date Assigned: 7/30/2025 | Due: 8/2/2025 |
| Date Completed: 7/31/2025 | |
| Description: | |
| Project manager has approved this project. | |