Submitter
| Submitter: Wastewater, MCE | Organization: MCCLELLAND CONSULTING ENGINEER |
| Address: 7302 Kanis Rd | City: Little Rock |
| State: AR | Zip: 72204- |
| Phone Number: (501) 371-0272 | E-Mail: lrww@mce.us.com |
Project Information
| Project ID: 138395 | Manager: Tanner Burns |
| Received: 6/30/2025 12:00:00 AM | Due: 9/25/2025 |
| Logged: 6/30/2025 | Closed: |
| Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Open |
| Summary: | |
| City of Booneville - Eastwood Pump Station Replacement, Southern Dr., Booneville**ONLINE** Fee $500 pd. . Letter; 138395 D7 C1 Booneville Eastwood Sewer Pump Station Replacement .docx; written 07/07/2025 - TRJ. (sent 07/11/2025) Letter; 138395 D7 C2 Booneville Eastwood Sewer Pump Station Replacement .docx; written 09/12/2025 - TRJ. (sent 09/18/2025) | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 6/30/2025 | Due: 7/10/2025 |
| Date Completed: 7/7/2025 | |
| Description: | |
| Letter; 138395 D7 C1 Booneville Eastwood Sewer Pump Station Replacement .docx; written 07/07/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 7/7/2025 | Due: 7/17/2025 |
| Date Completed: 7/11/2025 | |
| Description: | |
| Letter; 138395 D7 C1 Booneville Eastwood Sewer Pump Station Replacement .docx; written 07/07/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 7/11/2025 | Due: 7/14/2025 |
| Date Completed: 7/11/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 138395 D7 C1 Booneville Eastwood Sewer Pump Station Replacement .docx; written 07/07/2025 - TRJ. (sent 07/11/2025) | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 7/11/2025 | Due: 8/25/2025 |
| Date Completed: 9/12/2025 | |
| Description: | |
| Response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/5/2025 | Due: 9/15/2025 |
| Date Completed: 9/12/2025 | |
| Description: | |
| Letter; 138395 D7 C2 Booneville Eastwood Sewer Pump Station Replacement .docx; written 09/12/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 9/12/2025 | Due: 9/22/2025 |
| Date Completed: 9/17/2025 | |
| Description: | |
| Letter; 138395 D7 C2 Booneville Eastwood Sewer Pump Station Replacement .docx; written 09/12/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 9/17/2025 | Due: 9/20/2025 |
| Date Completed: 9/18/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 138395 D7 C2 Booneville Eastwood Sewer Pump Station Replacement .docx; written 09/12/2025 - TRJ. (sent 09/18/2025) | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 9/18/2025 | Due: 11/2/2025 |
| Date Completed: | |
| Description: | |