Submitter
| Submitter: Johnson, Zach | Organization: Hawkins-Weir Engineers, Inc. |
| Address: 110 South 7th Street PO BOX 648 | City: Van Buren |
| State: AR | Zip: 72956- |
| Phone Number: (479) 222-2014 | E-Mail: zachary.johnson@hawkins-weir.com |
Project Information
| Project ID: 138561 | Manager: Tanner Burns |
| Received: 7/14/2025 12:00:00 AM | Due: 8/28/2025 |
| Logged: 7/14/2025 | Closed: 8/25/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| Downtown Van Buren Water System Improvements, 2806 Bryan Road, Van Buren**ONLINE** Fee $500 PD. . Letter; 138561 D7 C1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 07/24/2025 - TRJ. (sent 08/01/2025) Letter; 138561 D7 A1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 08/14/2025 - TRJ. (sent 08/25/2025) | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/14/2025 | Due: 7/24/2025 |
| Date Completed: 7/24/2025 | |
| Description: | |
| Letter; 138561 D7 C1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 07/24/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 7/24/2025 | Due: 8/3/2025 |
| Date Completed: 7/31/2025 | |
| Description: | |
| Letter; 138561 D7 C1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 07/24/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 7/31/2025 | Due: 8/3/2025 |
| Date Completed: 8/1/2025 | |
| Description: | |
| Send comment letter and wait for a reply. Letter; 138561 D7 C1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 07/24/2025 - TRJ. (sent 08/01/2025) | |
| Assigned To: 43 | Action: Reminder to follow-up |
| Date Assigned: 8/1/2025 | Due: 9/15/2025 |
| Date Completed: 8/12/2025 | |
| Description: | |
| response received. | |
| Assigned To: 43 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/8/2025 | Due: 8/18/2025 |
| Date Completed: 8/14/2025 | |
| Description: | |
| Letter; 138561 D7 A1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 08/14/2025 - TRJ. | |
| Assigned To: 213 | Action: Supervisor Review |
| Date Assigned: 8/14/2025 | Due: 8/24/2025 |
| Date Completed: 8/19/2025 | |
| Description: | |
| Letter; 138561 D7 A1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 08/14/2025 - TRJ. | |
| Assigned To: 43 | Action: Finalize and Send Letter |
| Date Assigned: 8/19/2025 | Due: 8/22/2025 |
| Date Completed: 8/25/2025 | |
| Description: | |
| Project manager has approved this project. Letter; 138561 D7 A1 Downtown Van Buren Water System Improvements - Van Buren.docx; written 08/14/2025 - TRJ. (sent 08/25/2025) | |