Submitter
| Submitter: Homeyer, Ron | Organization: CIVIL ENGINEERING, INC |
| Address: P. O. BOX 12 | City: SILOAM SPRINGS |
| State: AR | Zip: 72761- |
| Phone Number: (479) 524-9956 | E-Mail: ron@civilengineeringss.com |
Project Information
| Project ID: 138565 | Manager: Jeff Stone |
| Received: 7/14/2025 12:00:00 AM | Due: 8/17/2025 |
| Logged: 7/14/2025 | Closed: 7/28/2025 |
| Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
| Summary: | |
| Stock Tank Liquor Water Extension, 350 N Progress Ave, Siloam Springs**ONLINE** Fee $370 PD | |
| Assigned To: 242 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/14/2025 | Due: 7/24/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Sent 1st Comment Letter to JS. | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 7/14/2025 | Due: 7/24/2025 |
| Date Completed: 7/14/2025 | |
| Description: | |
| Sent 1st Comment Letter to JS. | |
| Assigned To: 242 | Action: Finalize and Send Letter |
| Date Assigned: 7/14/2025 | Due: 7/17/2025 |
| Date Completed: 7/17/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 242 | Action: Reminder to follow-up |
| Date Assigned: 7/17/2025 | Due: 8/31/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Assigned To: 242 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/28/2025 | Due: 8/7/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Sent 1st Approval Letter to JS. | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 7/28/2025 | Due: 8/7/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Sent 1st Approval Letter to JS. | |
| Assigned To: 242 | Action: Finalize and Send Letter |
| Date Assigned: 7/28/2025 | Due: 7/31/2025 |
| Date Completed: 7/28/2025 | |
| Description: | |
| Project manager has approved this project. | |