Submitter
| Submitter: Franks, Anthony L | Organization: A.L. Franks Engineering |
| Address: 118 E Broad Street | City: Texarkana |
| State: AR | Zip: 71854- |
| Phone Number: (870) 216-1906 | E-Mail: |
Project Information
| Project ID: 138725 | Manager: Dennis Taylor |
| Received: 7/22/2025 12:00:00 AM | Due: 8/11/2025 |
| Logged: 7/22/2025 | Closed: 8/5/2025 |
| Classification: Funding Application | Status: Closed |
| Summary: | |
| CITY OF MCNEIL WWAC#7669, REHAB WATER SUPPLY. ONE REPORT SUBMITTED, NO FEES | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/22/2025 | Due: 8/1/2025 |
| Date Completed: 7/30/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 7/30/2025 | Due: 8/9/2025 |
| Date Completed: 7/30/2025 | |
| Description: | |
| Reviewed and forwarded to Chief Engr for signature. DET 7-30-2025 | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 7/30/2025 | Due: 8/9/2025 |
| Date Completed: 8/5/2025 | |
| Description: | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 8/5/2025 | Due: 8/8/2025 |
| Date Completed: 8/5/2025 | |
| Description: | |
| Project manager has approved this project. | |