Submitter

Submitter: PE, NicholasOrganization: Mickle Griffin Engineers & Surveyors
Address: 3434 Country Club AveCity: FORT SMITH
State: ARZip: 72903-
Phone Number: (479) 649-8484E-Mail: ngriffin@micklegriffin.com

Project Information

Project ID: 138821Manager: Tanner Burns
Received: 7/28/2025 12:00:00 AMDue: 9/4/2025
Logged: 7/28/2025Closed: 9/3/2025
Classification: Sewer Improvemnts(Non-Subdiv.)Status: Closed
  
Summary:
Fort Chaffee Redevelopment Authority Area 7 Sanitary Sewer Line Extension, H Street and Interstate 49, Barling**ONLINE** Fee $500 pd. . Letter; 138821 D7 C1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/04/2025 - TRJ. (sent 08/08/2025) Letter; 138821 D7 A1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/25/2025 - TRJ. (sent 09/03/2025)
Assigned To: 43Action: Review, Comment and/or Approve
Date Assigned: 7/28/2025Due: 8/7/2025
Date Completed: 8/4/2025
Description:
Letter; 138821 D7 C1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/04/2025 - TRJ.
 
Assigned To: 234Action: Supervisor Review
Date Assigned: 8/4/2025Due: 8/14/2025
Date Completed: 8/5/2025
Description:
Letter; 138821 D7 C1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/04/2025 - TRJ.
 
Assigned To: 43Action: Finalize and Send Letter
Date Assigned: 8/5/2025Due: 8/8/2025
Date Completed: 8/8/2025
Description:
Send comment letter and wait for a reply. Letter; 138821 D7 C1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/04/2025 - TRJ. (sent 08/08/2025)
 
Assigned To: 213Action: Supervisor Review
Date Assigned: 8/5/2025Due: 8/15/2025
Date Completed: 8/7/2025
Description:
 
Assigned To: 43Action: Finalize and Send Letter
Date Assigned: 8/7/2025Due: 8/10/2025
Date Completed: 8/8/2025
Description:
Send comment letter and wait for a reply. Letter; 138821 D7 C1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/04/2025 - TRJ. (sent 08/08/2025)
 
Assigned To: 43Action: Reminder to follow-up
Date Assigned: 8/8/2025Due: 9/22/2025
Date Completed: 8/8/2025
Description:
 
Assigned To: 43Action: Reminder to follow-up
Date Assigned: 8/8/2025Due: 9/22/2025
Date Completed: 8/25/2025
Description:
Response received
 
Assigned To: 43Action: Review, Comment and/or Approve
Date Assigned: 8/15/2025Due: 8/25/2025
Date Completed: 8/25/2025
Description:
Letter; 138821 D7 A1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/25/2025 - TRJ.
 
Assigned To: 213Action: Supervisor Review
Date Assigned: 8/25/2025Due: 9/4/2025
Date Completed: 9/2/2025
Description:
Letter; 138821 D7 A1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/25/2025 - TRJ.
 
Assigned To: 43Action: Finalize and Send Letter
Date Assigned: 9/2/2025Due: 9/5/2025
Date Completed: 9/3/2025
Description:
Project manager has approved this project. Letter; 138821 D7 A1 Fort Chaffee Redevelopment Authority H Street Sewer Line extension - Barling.docx; written 08/25/2025 - TRJ. (sent 09/03/2025)