Submitter
| Submitter: Johnson, Dana | Organization: Spears Engineering |
| Address: 3605 Jefferson Ave | City: Texarkana |
| State: AR | Zip: 71854- |
| Phone Number: (870) 774-3204 | E-Mail: dana@spearsengineering.com |
Project Information
| Project ID: 138873 | Manager: Dennis Taylor |
| Received: 7/30/2025 12:00:00 AM | Due: 8/19/2025 |
| Logged: 7/30/2025 | Closed: 8/18/2025 |
| Classification: Misc. Reports Water/Sewer | Status: Closed |
| Summary: | |
| CITY OF FULTON ENVIRONMENTAL REVIEW, WATER AND SEWER IMPROVEMENTS. ONE REPORT SUBMITTED, NO FEES | |
| Assigned To: 248 | Action: Review, Comment and/or Approve |
| Date Assigned: 7/30/2025 | Due: 8/9/2025 |
| Date Completed: 8/14/2025 | |
| Description: | |
| Assigned To: 83 | Action: Supervisor Review |
| Date Assigned: 8/14/2025 | Due: 8/24/2025 |
| Date Completed: 8/15/2025 | |
| Description: | |
| 1388730 dated 8-15-2025 Acceptance of Environmental Review for waterline replacements and City Park Pump Station improvements for Fulton AR. OK to mail/Email//upload to portal. OK to mail/Email/upload to portal. DET 8-15-2025. | |
| Assigned To: 248 | Action: Finalize and Send Letter |
| Date Assigned: 8/15/2025 | Due: 8/18/2025 |
| Date Completed: 8/18/2025 | |
| Description: | |
| Project manager has approved this project. | |
| Assigned To: 246 | Action: Billing |
| Date Assigned: 8/15/2025 | Due: 8/25/2025 |
| Date Completed: 8/15/2025 | |
| Description: | |
| NO PLAN REVIEW FEE REQUIRED. | |