Submitter
| Submitter: Jr, Ronald | Organization: Springdale Water Utilities |
| Address: 526 Oak Avenue | City: Springdale |
| State: AR | Zip: 72765- |
| Phone Number: (479) 927-4187 | E-Mail: rwatkins@springdalewater.com |
Project Information
| Project ID: 138968 | Manager: Dean Gernon |
| Received: 8/7/2025 12:00:00 AM | Due: 8/27/2025 |
| Logged: 8/7/2025 | Closed: |
| Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Open |
| Summary: | |
| Specification Requirements for the Construction of Water and Sewer Facilities, 526 Oak Avenue, Springdale**ONLINE** NO FEE NEEDED | |
| Assigned To: 237 | Action: For Your Information |
| Date Assigned: 8/7/2025 | Due: 8/17/2025 |
| Date Completed: 8/12/2025 | |
| Description: | |
| Moved to AP on 8/12/25 as he sent out the letter requesting the newer specifications. dbg | |
| Assigned To: 153 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/12/2025 | Due: 8/22/2025 |
| Date Completed: 8/22/2025 | |
| Description: | |
| C1Ltr 08/22/25 | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 8/22/2025 | Due: 9/1/2025 |
| Date Completed: 8/28/2025 | |
| Description: | |
| C1Ltr 08/22/25 | |
| Assigned To: 18 | Action: Supervisor Review |
| Date Assigned: 8/28/2025 | Due: 9/7/2025 |
| Date Completed: 9/12/2025 | |
| Description: | |
| Assigned To: 153 | Action: Finalize and Send Letter |
| Date Assigned: 9/12/2025 | Due: 9/15/2025 |
| Date Completed: 9/12/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 153 | Action: Reminder to follow-up |
| Date Assigned: 9/12/2025 | Due: 10/27/2025 |
| Date Completed: | |
| Description: | |