| Project ID: 139094 | Manager: Jeff Stone |
| Received: 8/19/2025 12:00:00 AM | Due: 10/1/2025 |
| Logged: 8/19/2025 | Closed: |
| Classification: Sub. Public Water, Pub Sewer | Status: Open |
| Summary: | |
| Jacobs Crossing Phases 4-5, Don Tyson Pkwy and George Anderson Rd, Springdale**ONLINE** Fee $500 pd | |
| Assigned To: 237 | Action: For Your Information |
| Date Assigned: 8/19/2025 | Due: 8/29/2025 |
| Date Completed: 8/19/2025 | |
| Description: | |
| Moved to CLM on 8/19/25 dbg | |
| Assigned To: 242 | Action: Review, Comment and/or Approve |
| Date Assigned: 8/19/2025 | Due: 8/29/2025 |
| Date Completed: 8/19/2025 | |
| Description: | |
| Sent 1st Comment Letter to JS. | |
| Assigned To: 234 | Action: Supervisor Review |
| Date Assigned: 8/19/2025 | Due: 8/29/2025 |
| Date Completed: 8/20/2025 | |
| Description: | |
| Sent 1st Comment Letter to JS. | |
| Assigned To: 242 | Action: Finalize and Send Letter |
| Date Assigned: 8/20/2025 | Due: 8/23/2025 |
| Date Completed: 8/21/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 242 | Action: Reminder to follow-up |
| Date Assigned: 8/21/2025 | Due: 10/5/2025 |
| Date Completed: 9/16/2025 | |
| Description: | |
| Assigned To: 242 | Action: Review, Comment and/or Approve |
| Date Assigned: 9/11/2025 | Due: 9/21/2025 |
| Date Completed: 9/11/2025 | |
| Description: | |
| Sent 1st Approval Letter to DBG. | |
| Assigned To: 234 | Action: For Your Information |
| Date Assigned: 9/11/2025 | Due: 9/21/2025 |
| Date Completed: 9/16/2025 | |
| Description: | |
| Sent 1st Approval Letter to DBG. Supervisor review by DG in JS absence | |
| Assigned To: 204 | Action: Supervisor Review |
| Date Assigned: 9/11/2025 | Due: 9/21/2025 |
| Date Completed: 9/16/2025 | |
| Description: | |
| Provided notes to CLM, switch to C2 letter | |
| Assigned To: 242 | Action: Finalize and Send Letter |
| Date Assigned: 9/16/2025 | Due: 9/19/2025 |
| Date Completed: 9/16/2025 | |
| Description: | |
| Send comment letter and wait for a reply. | |
| Assigned To: 242 | Action: Reminder to follow-up |
| Date Assigned: 9/16/2025 | Due: 10/31/2025 |
| Date Completed: | |
| Description: | |